Project Description
River Lea Diversion, Power Court, Luton
Hydraulic Modelling and Flood Risk Support
Client: Civic Engineers Limited
Date: 2024-2025
Luton Town FC’s ambitious redevelopment at Power Court required rerouting the River Lea to run around, rather than through, the future stadium site. Over 300 m of new concrete culvert were installed, and the original river route was blocked off to allow the river to flow via its new alignment.
The new river arrangement is designed not only to manage flows and flood risk, but also ultimately to become a riverside leisure and amenity corridor for supporters and local residents.
Kaya Consulting provided hydraulic modelling and flood risk support for the diversion of the River Lea as part of Luton Town FC’s Power Court redevelopment.
Our team developed detailed hydraulic models of the existing and proposed river alignments to assess conveyance capacity, flood risk impacts, and compliance with Environment Agency (EA) standards. The modelling informed the culvert and channel design, including inlet/outlet transitions, energy dissipation, and sensitivity testing under climate change and blockage scenarios.
Working collaboratively with civil engineers and landscape architects, Kaya ensured hydraulic performance was fully integrated with the site layout and public realm design. Through targeted technical engagement and model refinement, all EA concerns were resolved, allowing consent for the works to be secured.
The completed diversion, incorporating approximately 300 m of new culvert, now safely conveys the River Lea around the development site, reducing flood risk and unlocking the land for construction of the new stadium and associated infrastructure.